The Red/Purple Line Modernization project will be working on the tracks between Lawrence and Thorndale this weekend.
- Dates: Friday, May 22 to Tuesday, May 26, 2020
- Location: Red and Purple Lines – CTA southbound tracks from Lawrence Station to Thorndale Station
- Work Hours: 10pm Friday to 4am Tuesday (Continuous around-the-clock work)
- Work Activity: Contact Rail Replacement
Local Impact:
- A crane will be staged in the parking lot at 1130 W. Lawrence.
- There will be noise while work is being performed. Noise will include:
- General construction noise
- Metal on metal material handling
- Noise from rail equipment, crane and maintenance equipment
- Beeping for backup alarms on maintenance equipment and vehicles
- This is rolling construction work. No singular location outside of the area where the crane is staged will have constant noise while the work activity is taking place.