"There will be ongoing road and parking closures due to Metra bridge work and station construction. Full street closures are anticipated at Ravenswood during the following dates:
- Lawrence Ave. through Jan. 10 for bridge steel erection
- Leland Ave. Jan. 13-24 for bridge steel erection
- Wilson Ave. Jan. 27-Feb. 7 for bridge steel erection
Additionally, there are anticipated lane closures at Ravenswood during the following dates:
- Lawrence Ave. single-lane closure Jan. 13-17 for bridge steel detailing
- Leland Ave. single-lane closure Jan. 27-31 for bridge steel detailing"