Although this isn't in Uptown, it can affect your commute if you're going a few blocks west. (We've said a few choice words at being detoured!) From Ald. Martin's newsletter:

"There will be ongoing road and parking closures due to Metra bridge work and station construction. Full street closures are anticipated at Ravenswood during the following dates:
  • Lawrence Ave. through Jan. 10 for bridge steel erection
  • Leland Ave. Jan. 13-24 for bridge steel erection
  • Wilson Ave. Jan. 27-Feb. 7 for bridge steel erection

Additionally, there are anticipated lane closures at Ravenswood during the following dates:
  • Lawrence Ave. single-lane closure Jan. 13-17 for bridge steel detailing
  • Leland Ave. single-lane closure Jan. 27-31 for bridge steel detailing"