Latest Info On Metra Construction At Ravenswood

If you take travel west of Uptown by vehicle, this may help your commute. Ald. Martin's latest newsletter gives the latest schedules of closures for work being done on behalf of Metra at Ravenswood:

"There will be ongoing road and parking closures due to Metra bridge work and station construction. Full street closures are anticipated at Ravenswood during the following dates:
  • Wilson Ave. through January 24 for bridge steel erection
  • Sunnyside Ave. January 27-February 7 for bridge steel erection
  • Wilson Ave. January 27-February 7 for bridge steel erection
  • Montrose Ave. February 10-21 for bridge steel erection
  • Berteau Ave. February 24-March 6 for bridge steel erection

Additionally, there are anticipated lane closures at Ravenswood during the following dates:
  • Lawrence Ave. single-lane closure January 21 for bridge steel detailing"