Wilson Station Construction Update

The upcoming Sunnyside entrance/exit for the Wilson station
Looking north behind Aldi toward Wilson platform
The upcoming Sunnyside entrance/exit to the Wilson L is taking shape quickly. The ramps that will bring customers to and from the platform are in place.

The CTA wanted to let neighbors know of the coming week's construction activity:
"Foundations, demolition (should be the last week of demo), work at station entrances, steel erection (south end of project near Sunnyside working our way north.)

Impacting the community:

Wilson Avenue (from Broadway to Clifton) will be closed down 9am-4pm on Monday, Tuesday, Thursday and Friday for work activities at the station entrances.

Leland Avenue (from Broadway to Winthrop) and the alley next to the Clover Building (from Leland to just north of the Clover building) will be closed from now through early May to facilitate foundation installations. These are the last foundations to be installed on the north end of the project.
  • Pedestrians will still be able to pass on Leland.
  • Vehicles will need to enter and exit the alley from the North (Lawrence) during this period."