Thursday, March 24, 2016

4600 Block Of Broadway Closures For Construction

Date: 03/28/2016 – 04/01/2016

Work Hours: (Night Work) 8 PM – 5AM

Work Activity: Tie removal over Broadway & Steel Removal

Impact to Community: Broadway will be closed to vehicular traffic but open to pedestrian traffic

Limits of operation: Will be between Wilson & Broadway to Leland &Broadway

There will be dust/noise while work is being performed

2 comments:

  1. This, then, must be the beginning of the demolition of the old steel structure. Excellent!

    ReplyDelete
  2. They worked fast and have already demolished most of it from the existing platform south to where the new structure will tie in.